Riggin Residence ~Construction In Progress
Start of Work 7/14/2008
Move in Date 11/17/2008
Construction Duration: 5 months 2 days
Total Square Footage: 3,400 S.F.

Site Work Progress SystemBilt.com Progress
Plans-Elevations-1st & 2nd Floors Laying the Floor-7/14/2008
Lot & Site- 7/14/2008 Master Bedroom-7/21/2008
Clearing & Excavation-7/21/2008 Progress-8/15/2008
Footings-Rebar-Forms-7/28/2008 Progress-8/31/2008
Steel, Foundation-8/8/2008  
Stem Walls-8/8/2008  
Stem Wall Concrete-8/14/2008  
Backfill / Grading-8/18/2008  
Rough Plumbing & Electrical-8/22/2008l  
Concrete Prep & Slabs  
Garage Framing  
Systembilt Placement  
Piers-Decks  
Finish Gradework  
   

 

 
 

Joe Diloreto
Joe has been building residential and commercial structures in Santa Fe, New Mexico since 1976, and in Angel Fire since 1991. Joe and Diane established Moreno Valley Real Estate together in 2004. Joe is also a part-time real estate agent at RE/MAX, Angel Fire.

Diane Diloreto
Diane recently became a member of the RE/MAX, Angel Fire sales team. Diane has also distinguished herself as a top sales agent for National Recreation Properties International!

 
 
 
 
coyote crossing webmaster